Public opinion is split about the location for the new convention
center, the most expensive MAPS 3 project, although proximity to
Bricktown is key.
The convention center completion is plotted at the end of the preliminary MAPS 3 timeline.
News Clifton Adcock
A preliminary timeline for the eight individual MAPS 3 projects has been
made public, and although some involved with the projects are pleased
with the early schedule, others are not.
The MAPS 3 timeline could get revamped to hasten the convention center’s construction, pushing back completion dates for other major projects.
News Clifton Adcock
The recent MAPS 3
convention center subcommittee meeting pegged a site for the new center,
while a timeline approved by the group has major implications for
almost all other MAPS 3 projects.
The document that will guide MAPS 3 resource allocation and staffing priorities nears Oklahoma City Council approval.
News Clifton Adcock
The timeline arose after the subcommittee overseeing the MAPS 3 convention center requested a revised timeline from Architectural Design Group in order to speed up the convention center’s progress. With a price tag of more than $250 million, the convention center is the most expensive MAPS 3 project.
The Oklahoma City Council considers a MAPS 3 timeline that prioritizes convention center construction over quality-of-life projects.
News Clifton Adcock
Members of the Oklahoma City Council and several MAPS 3 subcommittees
expressed concern over a recommended timeline for MAPS 3 projects.